Five peoples do a task in ten days,then how much peoples do that task in five days?

Five peoples do a task in ten days, then how much peoples do that task in five days?

Many people answer this question in many ways but which is correct?

Brong Asked on February 8, 2018 in Mathematic.
Add Comment
1 Answer(s)

    Five peoples do a task in ten days,then how much peoples do that task in five days?

    • 10 days is needed for 5 people
    • 1 day is needed for 50 people
    • 5 day is needed for 10 people

    Ans : 10 people.

    Thanks

    Brong Answered on February 10, 2018.